GREEN BANK
Green Bank Telescope
Construction
The photograph on page 2, taken this September, shows that the
Green Bank Telescope (GBT) is
beginning to resemble its concept drawings now that the reflector
backup structure (BUS) has
been fully installed and the vertical feed arm started. The average
time for installation of each of
the 22 modules was two weeks.
Concurrent with the erection of the BUS modules, the 1,036
intermodule members were
reinstalled and welded. The intermodule members are needed to give the
BUS its integrity.
Temporary walkways were put up along the perimeter top and bottom
chords of the modules in
order to properly position and weld the intermodule members.
Actuators
Most of the active surface actuators were installed on the front
chords of the BUS modules prior
to lifting. Actuators which would interfere with the installation of
the intermodule members or
obstruct target areas were left off. These actuators were filled-in
when the modules were in place
atop the box structure. This fill-in operation started in April of
1998 and lasted until mid August.
Today, all 2,209 of the active surface actuators are in place while
more than 300 have been
accurately positioned.
Permanent Supports
The permanent supports function to carry the live and dead loads
incident upon the BUS back, or
down, to the box girder structure and thereby to the elevation shaft
which is supported by the
alidade and the foundation/ground. There are sixteen joints welded to
the back of the various
BUS modules. Of these, thirteen had to be redesigned, either to
reconfigure the joint to achieve
greater stress path efficiency or to correct bad welding. The rework
of the BUS joints began in
May 1998 and is now 84 percent complete. There are also 20
welded joints on the box structure
at various levels. The rework of these joints is 26 percent
complete. Of the 30 permanent beams
carrying loads between the BUS and box joints, two have been
installed.
Surface -- Actuator Cables
Actuator cable runs are currently being installed in the cable
raceways, from the proximate vicinity
of the actuators to the actuator control room. More than 50 percent
have been installed.
Installation is ahead of schedule.
Vertical Feed Arm
The vertical feed arm consists of 13 modules plus the feed/receiver
room and upper feed arm. By
the end of September 1998, the bottom two sections on each side of the
200-foot vertical feed
arm will be in place on the outboard end of the horizontal feed arm.
Two additional sections, and
the platform which supports the feed/receiver room, have been
assembled and await erection
along with the upper feed arm and feed/receiver building. The upper
60-foot portion of the feed
arm has been trial erected at the site including the deployable prime
focus boom, the prime focus
rotation mount, the subreflector, and the subreflector adjustment
mechanism. The feed arm servo,
which controls the above equipment had been installed and preliminary
tests run. The
feed/receiver room, which is located directly below the upper feed
arm, has been located nearby
with the secondary focus feed turret in its roof. In October-November
1998, the upper feed arm
servo will be operated continuously for at least a month. Additional
photogrammetric
measurements will be made to allow final setting of the subreflector
surface to a tolerance
somewhat better than 0.004 inches RMS. The vertex platform has
been installed on the telescope,
and the access walkways to the vertical feed arm have been installed.
Recently, the Contractor sent 20 surface panels to the site to test
shipping, handling, installation,
and alignment procedures. The panels were unpainted so that they
might be returned to the
Contractor's plant for remeasurement on the contour measurement
machine (CMM). This will
provide an evaluation of the above procedures with respect to any
deterioration of surface
tolerances. NRAO has provided a prototype panel corner setting tool
which the Contractor is
using to familiarize his personnel with its operation in anticipation
of the panel installation work.
R. D. Hall
Phil Jewell Returns to NRAO
It is a pleasure to announce the appointment of Philip R. Jewell as
Assistant Director - Green
Bank Operations. Phil is returning to the NRAO after three years on
the staff of the James Clerk
Maxwell Telescope in Hawaii. He had been on the NRAO staff for twelve
years prior to that,
most recently serving as deputy site director in Tucson. We are
delighted to welcome him back in
his new capacity. He will assume responsibility for the
Green Bank site on January 1, 1999.
Phil is replacing Jay Lockman as site director. After six years of
service in this position Jay has
asked to be relieved of his management responsibilities to allow him
more time for his research.
On behalf of the Observatory and its user community I want to thank
Jay for the outstanding job
he has done. We are all pleased that Jay will remain in Green Bank
and continue to provide
leadership there as a senior member of the scientific staff.
P. A. Vanden Bout
Green Bank Computing Developments
As part of the observatory-wide computer upgrade, we upgraded only
three of our older Suns.
One of these systems will replace the central server (sadira) later
this year when the appropriate
disks are delivered and configured. In line with the rest of the
Observatory, several other Suns
will be replaced by PCs running Linux. We have already procured two
such systems to start the
process of migration, and several others are planned for later in the
year. One of these was to
enable the system administrator to develop the Linux installation and
support procedures for the
public systems and GBT control computers. This uses the NRAO Linux
distribution maintained
and distributed from Charlottesville. In addition, the GBT Monitor and
Control system now
completely supports communication between systems of different
architecture (e.g., Suns and
PCs); this will allow Linux PCs to control the GBT.
We have a need to track the component maintenance history on the
GBT, so we are actively
tracking the progress of the newly acquired product for this purpose
on the VLA and VLBA in
New Mexico. The support for the VLA and VLBA is expected early next
year. Initially, we will
use the product on the server in Socorro. If, as expected, we decide
to adopt the package, a
second copy will be purchased for the local Green Bank server.
At long last, we have a new PBX in Green Bank. You can now leave
messages reliably using its
voice mail service. The long distance service has been switched to
FTS2000, which eliminates the
long delays in placing calls, gives lower noise connections, and
provides automatic billing. We
also have a new terminal server with a new modem bank to provide
modern dial-in capabilities up
to 33.6 kbps.
G. C. Hunt
NSF Grant Award for Informal Science Education
The National Science Foundation's Informal Science Education
Division recently awarded
$1,089,873 to NRAO, Green Bank, for a project entitled "Catching the
Wave: Enhancing the
NRAO Public Education Program."
The objective of the project is to design and implement an informal
science education program
that improves science literacy, instills appreciation for science and
the work of scientists and
engineers, and explores the relationship between science and
technology.
"Catching the Wave" is designed to be a series of interactive
exhibits, data displays and programs
that will bring visitors closer to the actual research being conducted
with the telescopes. Exhibits
will be designed around a set of questions or themes based on
scientific ideas associated with
radio astronomy. Staff at Green Bank will work with an advisory
committee composed of
museum educators and evaluators, teachers, and tourism personnel.
"Catching the Wave" will target rural Appalachian students who have
limited access to informal
science centers. Therefore, a critical component of the project will
be programming for K12
student visitors. Here, Green Bank staff will seek the expertise of
educators from West Virginia
and the surrounding regions. Instructional programs will compliment
local instructional goals and
national goals as set forth in the National Science Education
Standards.
The project will continue over the next three years, resulting in a
robust public education program
and increased tourism to the Green Bank site.
S. A. Heatherly
A Workshop on the Square Kilometer Array
Green Bank is hosting a workshop on the Square Kilometer Array on
October 9 and 10, 1998.
The workshop will be an opportunity to address the desirability of the
participation by the US in
the Square Kilometer Array project, which at present is largely being
investigated at Dwingeloo,
Penticton, and CSIRO/ATNF. Several US centers have begun work as
well, and the workshop
will be a good opportunity to compare notes and to seek out wider US
interest.
Two recent international workshops have been held: At Sydney in December 1997 and at Calgary in July 1998 (earlier workshops were held in the Netherlands at Leiden and Delft). These will be summarized for discussion.
There are six general topics on the agenda:
1. Summary of SKA activities and rationale to date
2. Summary of Calgary and Sydney science workshops
3. Current concepts
4. Technical issues
5. Strategic issues
6. General discussion
The workshop web page is: (ht
tp://www.gb.nrao.edu/~rfisher/SKAworkshop/skaworkshop.html).
J. R. Fisher
MILLIMETER ARRAY
Status of the Millimeter Array
The three months since the last NRAO Newsletter have been
exceptionally busy for the staff
involved with the MMA Project. Strong bonds have been established with
the Republic of Chile;
the first comprehensive review of the project led to revisions of the
project emphasis; the NSF
oversight committee made several suggestions that benefit the project
and focus our efforts; and
there have been important developments in Europe that are expected to
lead to an enhanced
project.
In July, Associated Universities, Inc., (AUI) received final
approval from the Foreign Ministry of
the Republic of Chile to establish and operate an observatory in Chile
under the same terms and
conditions that other foreign observatories operate there. We are
grateful to our many colleagues
in Chile for their support and encouragement in making this happen.
We are committed to
making the MMA of mutual benefit to both our communities through a
continuing partnership.
Also in July the President of the Republic, with the approval of
the Mining Ministry, declared the
Chajnantor site to be a science preserve for the MMA and other
scientific facilities requiring the
exceptionally dry and transparent atmosphere that this site offers. In
a separate declaration the
Chilean science agency, CONICYT, was named to administer use of the
preserve. These
declarations were made in ceremony at La Moneda, the Presidential
Palace, attended by
representatives of the Republic of Chile, AUI, NSF, NRAO, and Chilean
universities and
observatories.
The month of July ended with an Internal Project Review. At this
occasion all the people working
on the MMA, together with the university-based MDC participants and
representatives of the
MAC, met to review the work planned in the MMA Design and Development
phase. These plans
were summarized for the group in the initial draft of the MMA Project
Book. The purpose of the
review was to identify issues that need resolution, issues either
missing from the Project Book, or
issues requiring a restructuring of the work presented in the Project
Book. The Project Book and
a summary of the issues raised at the Project Review can be found on
the MMA web pages.
August began with the second review of the MMA project by the NSF
MMA Oversight
Committee (MMAOC). The MMAOC at an earlier meeting had made
recommendations for an
acceleration of the antenna procurement, a recommendation that the
project implemented; the
implementation was reviewed in August. One of the ramifications was
the antenna vendor's
meeting described in an accompanying article in this Newsletter.
Other recommendations of this
and the earlier meeting emphasize the need for comprehensive project
management structures.
This recommendation is also being implemented. The MMAOC reviews are
archived and
available via the MMA web pages.
In September there were several gatherings of scientists and their
science consortia and ministers
interested in merging the European LSA project with the MMA.
Significant progress appears to
have been made toward the definition of a common effort in Europe.
There is every reason to be
optimistic that such an LSA/MMA merger will in fact become a reality.
In October we will concentrate on getting the Work Breakdown
Structure for the MMA complete
and firmly in place for the D&D phase of the project. The project
will be reviewed by the MAC
at a meeting in Chicago November 21. If there are issues you would
like to bring to the attention
of the MAC, please contact one of the committee members. As you would
expect, the MAC
membership is also on the MMA web pages (click on library). In fact,
the primary means of
communication between the MMA and the community is electronic: The MMA
e-news is
circulated in e-mail at regular intervals; to subscribe contact Kate
Weatherall
(kweather@nrao.edu).
R. L. Brown
Antenna Progress and Plans
The Antenna Group has just completed the Antenna Preliminary Design
Review (PDR) that was
held during an Internal Project Review in August. Antenna
requirements are documented in the
MMA Project Book in chapter 4 can be found at:
(http://www.tuc.nrao.edu/~demerson/project_book/chap4/chap4.html).
We held a Vendor
Information Meeting in Tucson on September 22 to introduce vendors to
the antenna designs and
the planned procurement process. This meeting was advertised in the
CBDNet
(http://cbdnet.access.gpo.gov)
on August 4, 1998, and published in the Commerce Business Daily
on August 7, 1998. Twenty-five companies from the US and Europe
attended the meeting. The
antenna Critical Design Review (CDR) is planned for a date to be
determined in
November/December 1998. The RFP is planned to be issued in January
1999 with bid response in
April 1999. Delivery of the antenna is scheduled for June 2001.
Two designs are being studied covering a wide parameter
space in antenna design (see page 5).
The NRAO Design (http://www.t
uc.nrao.edu/~jkingsle/nraonl/nrao2.jpg) is based on the BIMA
6-meter antenna. This design has evolved from a millimeter wave
8-meter antenna into a high
performance submillimeter 10-meter antenna. The OVRO design
(http://www.t
uc.nrao.edu/~jkingsle/nraonl/ovro2.jpg) is similar in some
respects to the JCMT and
OVRO antennas with a novel metrology system and a wheel and track
base. Both designs have
incorporated innovative ideas to meet the challenging specifications
of the MMA. Currently, both
groups are working on completing designs and issuing design reports.
The next task will be to
convert antenna requirements into RFP specifications.
J. S. Kingsley
VLA
VLA Upgrade Project Status
On June 29 and 30, approximately fifty scientists and engineers
came to Socorro to discuss the
VLA Upgrade Project with an approximately equal number of local staff.
The goals of this
meeting include a review of the project plans as developed so far by
NRAO staff, discussion of
the interaction of this project with the MMA, SKA, and other astronomy
initiatives, and review of
the key science benefits of the upgrade.
Work on the upgrade will now focus on preparing our presentation to
the Decade Review
Committee. The technical aspects of the plan will continue to be
developed, and we will continue
to add to the list of key science projects which would be benefitted
by an upgrade. Readers of
this newsletter who wish to contribute to this latter effort are
invited to do so by contacting me at:
rperley@nrao.edu. A summary of the
upgrade's capabilities is also available by contacting me.
R. A. Perley
VLA-Pie Town Link
Construction and testing of hardware and software are continuing
for the first fringe test of the
fiberoptic link of the Pie Town VLBA antenna to the VLA. These
tests will involve the operation
of Pie Town in conjunction with a 4-antenna subset of the VLA. This
requires modification of
two delay cards for the single IF of each antenna being used in the
test. Modification of the cards
for all antennas and all IFs will commence only after the first
fringes are acquired, and the test
results well understood.
Current plans are for initial testing of the Pie Town equipment to
take place at the VLA during
the first half of November, with a single VLA antenna being used to
mimic Pie Town. After that
time, the rack of equipment used to send the IF signal and the
monitor/control information across
the fiber link will be moved to Pie Town, and first tests will
commence in late November.
We note that November is a very busy time at the VLA and the VLBA,
including a tight VLA
schedule leading up to the configuration change in the middle of the
month, as well as VLBA
participation in the sessions of the Coordinated Millimeter VLBI Array
and the Global VLBI
network. In addition, a major modification of the VLA control room is
expected to take place in
November. Coordination of the tests of the VLA-Pie Town link with
these activities, as well as
normal scientific observing, is under way. In order to minimize the
disruption to users caused by
possible "on-the-fly" modifications to systems, tests will be
scheduled only when the VLA can be
devoted fully to those tests, rather than risking disruption of
scientific observations by using a
limited sub-array of the VLA. In addition, tests involving Pie Town
will take place only when that
antenna is not scheduled for VLBI observations.
For those interested in more information, minutes of the VLA-Pie
Town meetings and past
newsletter articles are now available on web at (http://www.nrao.edu/~
julvesta/vla_pt.html).
J. S. Ulvestad
VLA Configuration Schedule
Configuration | Starting Date | Ending Date | Proposal Deadline |
CnB | 30 Oct 1998 | 16 Nov 1998 | 1 Jun 1998 |
C | 20 Nov 1998 | 01 Feb 1999 | 1 Jun 1998 |
DnC | 12 Feb 1999 | 01 Mar 1999 | 1 Oct 1998 |
D | 05 Mar 1999 | 01 Jun 1999 | 1 Oct 1998 |
A | 18 Jun 1999 | 27 Sep 1999 | 1 Feb 1999 |
BnA | 08 Oct 1999 | 25 Oct 1999 | 1 Jun 1999 |
B | 29 Oct 1999 | 14 Feb 2000 | 1 Jun 1999 |
The maximum antenna separations for the four VLA configurations are: A-36 km, B-11 km, C-3 km, D-1 km. The BnA, CnB, and DnC configurations are the hybrid configurations with the long north arm, which produce a round beam for southern sources (south of about -15 degrees declination) and extreme northern sources (north of about 80 degrees declination).
Approximate Long-Term Schedule
Q1 | Q2 | Q3 | Q4 | |
1998 | D,A | A | B | C |
1999 | D | D,A | A | B |
2000 | C | C,D | D | A |
2001 | B | B,C | C | D |
2002 | A | A,B | B | C |
Observers should note that some types of observations are
significantly more difficult in daytime
than at nighttime. These include observations at 327 MHz (solar and
other interference; disturbed
ionosphere, especially at dawn), line observations at 18 and 21 cm
(solar interference),
polarization measurements at L band (uncertainty in ionospheric
rotation measure), and
observations at 2 cm and shorter wavelengths in B and A configurations
(tropospheric phase
variations, especially in summer). They should defer such observations
for a configuration cycle to
avoid such problems. In 1998, the C configuration daytime will be
about 18h RA and in 1999 the
D configuration daytime will be about 2h RA.
Time will be allocated for the VLBA on intervals approximately
corresponding to the VLA
configurations, from those proposals in hand at the corresponding VLA
proposal deadline. The
VLBA spends about half of available observing time in coordinated
observations with other
networks, with the scheduling dictated by those networks. In
decreasing order of the time
devoted to the observations, these are HALCA space VLBI, Combined
Millimeter VLBI Array,
Global astronomical VLBI with the EVN, and geodetic arrays coordinated
by GSFC.
Any proposal requesting NRAO antennas and antennas from two or more institutions affiliated with the European VLBI network is a Global proposal, and must be sent to the EVN scheduler as well as to the NRAO. VLBA proposals requesting only one EVN antenna, or requesting unaffiliated antennas, are handled on a bilateral basis; the proposal should be sent to both NRAO and the operating institution of the other antenna requested. Coordination of observations with non-NRAO antennas, other
than members of the EVN and the DSN, is the responsibility of the
proposer.
B. G. Clark
1612 MHz OH Observing at the VLA
Tests performed in August and September 1998, the start of
full-time activation of the IRIDIUM
constellation of communication satellites, show that a large fraction
of data taken at 1612 MHz is
severely corrupted. This is likely due to saturation in the VLA
electronics by the main downlink
of the IRIDIUM satellites at 1621-1627 MHz. These effects are more
severe than anticipated and
advertised in the previous newsletter. Further tests are underway.
Note that any VLA or VLBA observation of OH at 1667 MHz redshifted
into the main IRIDIUM
space to Earth downlink between 1621 and 1627 MHz (8300 to 6800 km/s)
will be severely
compromised. Observations of lines within ± 10 MHz (± 2000
km/s) of the main Iridium
downlink frequencies may be corrupted.
G. B. Taylor and D. S. Bagri
New Mexico Computing Developments
At the Array Operations Center, we have recently begun official
support and installation of
Intel/Linux based PCs. The decision to begin support was based on
several factors: performance
versus Sparc/Solaris, an existing installed base which required more
centralized support, and
increased local Linux expertise as a result of recent changes in
staffing.
Four new 400 MHz PCs were purchased with RedHat Linux 5.1
installed. With help from NRAO
Charlottesville, we are now in a position to install Linux machines in
a simple, consistent manner,
making central administration feasible. For those who are interested
in issues concerning
centralized administration of Linux PCs, contact James Robnett, jrobnett@nrao.edu. Aipsmarks
on the newest machines, 400 MHz Pentium-IIs with two 9GB Ultra-wide
SCSI disks and 128 MB
of memory, are slightly above 14. An effort is under way to add
third-party software to
eventually offer the same variety of choices as under Solaris. We
expect to add more of these or
similar machines in the fall of 1998.
The two remaining public Sparc-20 workstations were replaced with
Ultra 10 machines. This
means that all public machines at the AOC are Sun Ultras. We have no
plans to move public
workstations to the Intel platform until we have gained more
experience with it.
An effort is well underway to select a new AOC server to replace
arana, the Auspex server that
has served us well for many years. We expect to finish the selection
process in the second half of
September and purchase and install the new machine in the following
months. The fiber optic
installation at the VLA site was completed, resulting in vastly
enhanced computing connectivity to
and from the various buildings at the site.
A reorganization in the Computer Division took place: the VLA and
the VLBA online groups
were merged into the Array Support Group, headed by Steve Blachman.
The primary role of this
group will be to provide software support to enable the successful
operation of the VLA and
VLBA. This merger will enable us to allocate the extensive expertise
and resources, which until
now were divided among two groups, to either instrument as needed. We
believe a combined
group will be in a much stronger position to tackle upcoming large
projects.
A project was started to rewrite the VLA online system in order to
make it less dependent on the
Modcomp computers that currently are at the heart of the system. The
main reasons for this are
that there are serious concerns about the continued long-term
viability of the Modcomps and their
maintenance; the software is over a decade old; and the operator
interface imposes severe
restrictions on the efficient operation of the instrument. We intend
to use the rebuild as the first
part of a larger project to add new capabilities to the VLA and also
to position ourselves for any
future VLA upgrade. We have formed a formal project to be run by the
Array Support Group of
the Socorro Computer Division. The aim of the project will be to
determine the requirements for
the system rebuild, produce a formal written design document and,
following a critical review of
the design, implement the new system. This must be done while still
keeping the VLA fully
operational.
G. A. van Moorsel
Calibrators
In keeping with the times, the VLA and VLBA have just adopted the N9806 radio reference frame source coordinates from the USNO. The VLA calibrator manual has been updated online, and the next release of OBSERVE will have the updated source coordinates. The positions of 500 sources (nearly half the number in the VLA calibrator manual) were updated. Of these, three sources which were thought to have positions with an accuracy of better than 10 mas had coordinates that shifted by greater than 25 mas. The VLBA, and in rare instances the VLA, can provide an absolute astrometry better than 25 mas.
If a project used one of the following calibrators:
J1001-446=B0959-443 (calcode B was off by 75.3 mas),
J1218-460=B1215-457 (calcode B was off by 114.4 mas),
J1820-254=B1817-254 (calcode A was off by 28.4 mas),
and the goal was a high precision astrometry, then it is possible
that a correction needs to be
made. For more information, contact Greg Taylor at gtaylor@nrao.edu.
G. B. Taylor
CS Replaces Upcoming C Configuration
The entirety of the upcoming (fall 1998) C configuration will be
replaced by the CS (shortened C)
configuration. It is probable that all future C configurations will
be replaced by CS as well. This
configuration will be formed by moving the antenna normally placed at
an intermediate position
along the north arm (N10) into a central location (N1) to help fill in
the short-spacing hole (see
Braun 1993, Holdaway 1994, and Rupen 1997). This significantly
improves the array's sensitivity
to large structures, at the expense of some intermediate baselines.
The effects of the latter are
quantified in a detailed study of the uv-coverage and simulated images
resulting from both C and
CS configurations (Rupen 1998, available from NRAO or over the web as
VLA Scientific
Memorandum No. 175, accessible from the web at
(ht
tp://www.aoc.nrao.edu/doc/vla/html/Memos/scimemolist.shtml). In
accordance with this work
several steps will be taken to ensure the advantages of the new short
spacings without
compromising the uv-coverage of the standard C configuration:
1- If the observer states EXPLICITLY in the OBSERVE file that the
CS antenna at the central
pad (N1) is critical to the science, the observer will be guaranteed
the short-spacing coverage
provided by that antenna. There are two aspects to this guarantee.
First, someone will be called in
to fix this antenna when and if it fails, even if no other antennas
are down. Maintenance will
(insofar as possible) also be scheduled so as not to conflict with the
observations. Second, if the
antenna does go down for more than an hour during a
given observing run, this will be noted in
the log. If the PI then requests it, NRAO will make every effort to
schedule observing time on a
roughly 1-for-4-hour basis in the next D configuration to fill in the
missing short spacings.
Note that these special rules will not be in place, unless the
observer specifically requests such
special handling in the OBSERVE file.
Note also that, even with such a request, the D configuration
make-up time will not be granted
automatically-- the observer must explicitly request it, in response
to NRAO's notification in the
observing log that the CS antenna was not available. Obviously this
requires a timely response to
that notification.
2- If the OBSERVE file does not explicitly
designate the CS antenna at N1 as critical, those
observations will be assumed to be standard C configuration
observations. In this case the
antennas at N8 and N12, the two positions surrounding the
newly-vacated N10, will be
designated as critical antennas. This means that (1) if either of
these antennas goes down, every
effort (including immediate call-out) will be made to bring it back in
as soon as possible; and (2)
maintenance will (insofar as possible) be scheduled so as not to
conflict with these observations.
There is no guaranteed make-up time however.
Note that, while CS does provide a few short baselines, detection
experiments and observations of
very low surface brightness features are still best carried out in D
configuration.
M. P. Rupen
VLBA/VLBI
ARISE Science Workshop
A science workshop for the proposed future Space VLBI mission,
ARISE, was held in Green
Bank on August 19 and 20. About 30 attendees gathered to discuss
possible scientific goals of
the mission, and to set the specific scientific priorities. There was
a general consensus that the
mission as currently envisioned, with a 25-meter class orbiting
telescope that operates at
frequencies up to 86 GHz, is both scientifically exciting and
technically realizable. The consensus
of the workshop attendees will be used to generate a more detailed
science "white paper," which
will be produced by the end of the year. The most important
scientific goals, agreed on at the
workshop, are listed below.
Primary Goals:
(1A) Black holes and other compact objects: How are they fed and
what do they do with the fuel?
(1B) Accretion disks: What is the physics, and the connection, of
big disks, little disks, and
compact central objects, both in active galaxies and in active binary
stars and star-forming regions
in our own Galaxy?
Secondary Goals:
(2A) Gravitational lenses: Explore the population of compact
objects in the mass range less than a
million solar masses, and use lenses as cosmic telescopes to enhance
angular and linear resolution
of distant objects.
(2B) Coronae in active stellar systems: Measure emission from
stellar coronae on scales smaller
than a stellar radius, and image highly polarized stellar flares to
probe for coherent emission
processes.
For more information about ARISE and related science and
technology, please consult the new
ARISE web site at (http://arise.jpl.nasa.gov/).
J. S. Ulvestad
VLBI Network Call For Proposals
Proposals for VLBI Global Network observing are handled by the
NRAO. There are usually four
Global Network sessions per year, with up to three weeks allowed per
session. The Global
Network sessions currently planned are:
Date | Bands | Proposals Due |
11 Nov to 02 Dec 1998 | 5 cm, 6 cm, 18 cm, 3.6 cm | 01 Jun 1998 |
11 Feb to 04 Mar 1999 | 6 cm, 18 cm, 0.7 cm? | 01 Oct 1998 |
27 May to 17 Jun 1999 | 6 cm, 18 cm, 3.6 cm? | 01 Oct 1998 |
09 Sep to 30 Sep 1999 | 6 cm, 18 cm, 1.3 cm? | 01 Feb 1999 |
12 Nov to 03 Dec 1999 | 6 cm, 18 cm, 5 cm? | 01 Jun 1999 |
Each session will probably comprise observations at three bands.
First priority will be HALCA
observations in the 6 cm and 18 cm bands. The third band for
each session has not been finally
chosen; the bands above marked with a question mark have been
suggested, but the final choice of
bands for sessions in 1999 has not yet been made.
It is recommended that proposers use a standard coversheet for
their VLBI proposals.
Fill-in-the-blanks TeX files are available by anonymous ftp from
ftp.cv.nrao.edu, directory
proposal or via the VLBA home page on the web. Printed forms, for
filling in by typewriter, are
available on request from Lori Appel, AOC, Socorro.
Any proposal requesting NRAO antennas and antennas from two or more
institutions in the
European VLBI network constitutes a Global proposal. Global proposals
must reach both
Network's Schedulers on or before the proposal deadline date; allow
sufficient time for mailing.
In general, fax submissions of Global proposals will not be accepted.
Proposals requesting use of
the Socorro correlator must be sent to NRAO even if they do not
request the use of NRAO
antennas; proposals for the use of the Bonn correlator must be sent to
the MPIfR if they do not
request the use of any EVN antennas. For Global proposals, or those
to the EVN alone, send
proposals to:
R. Schwartz Max Planck Institut fur Radioastronomie Auf dem Hugel 69 D 53121 Bonn, Germany
For proposals to the VLBA, or Global proposals, send proposals to:
Director, National Radio Astronomy Observatory 520 Edgemont Road Charlottesville, VA 22903-2475 USA.Proposals may also be submitted electronically, in Adobe Postscript format, to proposevn@hp.mpifr-bonn.mpg.de a> or propsoc@nrao.edu, respectively. Care should be taken to ensure that the Postscript files request the proper paper size.
B. G. Clark
The Smooth October 1 VLA and VLBA Proposal Deadline
The October 1, 1998 VLA and VLBA proposal deadline went very
smoothly, and we thank all of
you for your cooperation. Of the 175 proposals submitted, about half
arrived before the last
submission day--a new record, and we extend our extra special thanks.
About 85 percent of the
proposals now are submitted by e-mail.
A few considerations to keep in mind for future deadlines:
(1) If your proposal is larger than 5 Mbytes, it will be
automatically rejected, and you will receive
detailed instructions on how to submit the proposal via ftp.
(2) Please remember proposals must be in "pure" postscript format.
No other forms will be
accepted.
(3) Submit a proposal only once. If there is a problem printing
it, you will be informed as soon as
possible. This may take several hours on the proposal deadline day.
If you wish to submit a
revised proposal, please indicate clearly in the subject line that
this submission should take
precedence over a clearly specified previous submission.
L. S. Appel and J. L. Nance
12 METER
Improvements to the 12 Meter Telescope
During the 1998 summer shutdown period, the following improvements
were made to the 12
Meter Telescope system:
New digital correlator: See article below.
Filter bank adjustment: The filter bank
spectrometers require adjustment and cleaning each
summer shutdown. A number of bad channels were repaired and some
faulty components were
replaced.
Dome repair: The 12 Meter Telescope dome cover
was last replaced in September 1980. Mainly
due to an active repair and maintenance program developed by Jeff
Kingsley, the current dome
cover has lasted for approximately 18 years. Unfortunately, the dome
fabric has been decaying for
several years and is now badly in need of repair. During summer
shutdown the dome repair
activities consisted of re-stitching a number of seams in the fabric
and patching a number of tears
and holes in the material. In addition to the repair of the dome
fabric, the track and wheels, door
track and rollers, door arch beam, power track, and azimuth drive were
inspected and repaired
where necessary.
All of the 12 Meter front-end received their usual summer
clean-up; The cryogenic systems
were cleaned and repaired where necessary. A problem with the 3 mm LO
channel 1
mixer-feed-lens assembly (called a "rocket") was discovered and
repaired.
New IF cables: A section of the IF cable system
of the telescope was replaced with new Heliax
coaxial cable. This upgrade will improve the attenuation and frequency
response slope of the IF
signal distribution system.
Central selection mirror: The central selection
mirror friction drive bearings were replaced and
the drive was precisely aligned. This should improve the repeatability
of the system and remedy a
problem with position drift in this system.
Prime focus rebuild: The focus-translation mount
was outfitted with digital encoders in all three
axes (radial, north-south, and east-west focus) with a resolution of
± 2 microns. This unit was also
cleaned and lubricated. The existing LVDT analog drive system will be
used until a new digital
electronics drive system can be completed and tested. Much of this
work was done by Paul Greve,
a visiting engineering student from Grenoble.
NRAO Tucson home page: We have revised the NRAO
Tucson home page. New and updated
information has been added to this web site.
User's manual update: The 12 Meter User's Manual
has been revised. In addition to some
minor rearranging, the continuum and spectral line observing sections
have been rewritten and
several new appendices have been added. Comments on this document are
appreciated.
J. G. Mangum for the Tucson Staff
New Digital Correlator for the 12 Meter Telescope
A new digital auto correlator has been installed at the 12 Meter
Telescope. This new millimeter
correlator (MAC) follows closely the GBT correlator design and uses
the same type of correlator
chip. The MAC replaces the hybrid correlator which has been in use at
the telescope for
approximately ten years. The MAC will support the existing 1.3 mm and
3 mm, and any future,
multi-beam systems on the telescope. The MAC has an instantaneous
bandwidth of 950 MHz; the
old hybrid correlator system only supported 300 MHz in 8-beam mode.
300 MHz is inadequate
for some galactic observations at 1.3 mm, and inadequate for most
extra-galactic observations.
The MAC does not rely on hybrid technology, so it will avoid the
platforming and ramping
problems which existed in old hybrid correlator. Further information
on the MAC can be found at
(http://www.tuc
.nrao.edu/news/new_correlator.html).
J. G. Mangum for the Tucson Staff
IN GENERAL
Observatory-Wide Computing Developments
In recent months, much of the Observatory-wide computing effort has
focused on the
development of a status report and long-range plan for computing at
NRAO. The intent is to
cover all major aspects of computing at all sites. The document will
be used primarily for internal
planning purposes and will be updated annually.
One of the chronic problems in radio astronomy, which has been
steadily worsening over the past
few years, is the time required to load and back up large data sets
(i.e., up to tens of gigabytes).
As well as large overall size, we are beginning to see more VLBI
experiments with individual
files which, in FITS format, exceed the storage capacity of a single
high-density Exabyte tape;
these files therefore cannot be backed up on traditional tape media.
NRAO already has two
Digital Linear Tape (DLT) drives, one each in Socorro and
Charlottesville. While the capacity and
transfer rates of these drives have lived up to the claims for the
technology, we have some
concerns about the robustness of the hardware and the media for
general use. There are now
funds available to purchase several additional drives providing this
capacity (minimum 20 GB per
tape) and transfer speed (>3 MB/sec), and we have ordered two
Exabyte Mammoth drives for
evaluation. While these drives do not have quite the capacity or
speed of DLT, the hardware and
media are less expensive and may be more durable for use by many
different people. Results of
our tests will be reported in the next NRAO Newsletter.
Observatory-wide computing is also in the process of purchasing
enough licenses of an anti-virus
program to cover all PCs connected to our networks. One of the
features of this program is that it
can run continuously and scan all files downloaded from the Internet
or transferred from
removable media. While there has been no major virus propagation
within NRAO, they do appear
on small numbers of systems fairly regularly; this software should
reduce the frequency and spread
of viruses.
M. R. Milner
Charlottesville Computing Developments
As part of the Observatory-wide program to upgrade NRAO's rapidly
aging workstations,
Charlottesville took delivery of several Sparc Ultra 10 and Intel
Pentium II 450 systems. At the
time of writing, these are currently being deployed. One of these
Intel systems will replace a
public IBM RS/6000 system which has reached the end of its useful
life. The AIPS performance
as measured on the Intel systems is better than expected; details will
be made available on the
AIPS web pages as time permits.
In cooperation with systems personnel at the other main sites,
Charlottesville Computing staff has
set up a Windows NT server which acts as a "domain controller" in
conjunction with similar
servers in Green Bank and Socorro. It is expected that this will
greatly simplify the administration
of our pool of Windows-based PC systems. A personnel change occurred
this quarter. Jeff
Uphoff, who started out with the Computer Division almost five years
ago and who was perhaps
single-handedly behind the exploration, adoption and deployment of
Linux within NRAO, has left
us for greener pastures. He now works for a Silicon Valley start-up
called TransMeta; this is the
same company that hired Linus Torvalds. We wish Jeff the best with
his new responsibilities.
P. P. Murphy
AIPS++ Beta Release
The next AIPS++ beta release (our third) is planned for the week of
October 12. This release has
been long in the preparation but contains many, many changes from the
previous release, ranging
from improvements to the user interface to a number of new
applications and capabilities.
Following this release, we will switch to a rapid-update approach
whereby a new release of the
latest stable version of AIPS++ will be made monthly. This will enable
our beta-testers to receive
bug fixes more quickly and will also enable us to release new
functionality as it appears in the
system. This rapid-update approach will continue until our first
public release, planned for Spring
1999.
Recent news on the developments in AIPS++ and on the various uses
that AIPS++ is now being
put to can be found in our very successful newsletter series, edited
by Bob Hjellming and Kate
Weatherall. This, and other information about AIPS++, can be found
from our new home page at
(http://aips2.nrao.edu).
T. J. Cornwell
1998 and 1999 Summer Students
The 1998 Research Experiences for Undergraduates at the NRAO has ended with the 19 undergraduate students and four graduate students heading for their colleges from the four NRAO sites. As examples of the sorts of research conducted by students and their advisers at the four NRAO sites, interested parties may find a short summary of the research accomplished by the students on the web at: (http://www.cv.nrao. edu/~awootten/reu98.html).
Information and application forms have been mailed soliciting
applications for research
assistantships next summer. The majority of the assistantships will
be offered to undergraduate
students who are currently enrolled in US undergraduate institutions
and who will not receive
their degrees before or during the summer of 1999. We currently
anticipate that 15 positions will
be available in 1999. A limited number of assistantships will be
available for graduate students or
students from non-US institutions.
The deadline for receipt of application materials will be January 20, 1999; notice of decisions will be sent by March 1, 1999. Forms are available from department heads, on the web: (http://ww w.cv.nrao.edu/~awootten/summer-students.html) or by writing to:
National Radio Astronomy Observatoryc/o Program Director, Summer Student Program520 Edgemont RoadCharlottesville, VA 22903-2475H. A. Wootten