Papers of Barry G. Clark > Expanded Very Large Array (EVLA) Series
Collection Items
EVLA M&C System Milestones as of 08/29/2001
Description:
Projected timeline
Start Date:
2001-08-29
EVLA Operation's System Software Requirements Specification (SRS)
Start Date:
2001-11-09
EVLA Antenna Monitor & Control Subsystem Preliminary Requirements Specification
Start Date:
2001-11-15
Notes on space at the VLA site
Start Date:
2002-06-03
EVLA on Antenna Test Plan
Start Date:
2003-05-00
Antenna 13 overhaul
Start Date:
2003-06-05
EVLA Software Design
Start Date:
2004-06-14
Requirements and Functional Specification: EVLA Correlator Chip
Start Date:
2005-02-15
EVLA Correlator Chip ASIC - Production Signoff Critical Design Review
Start Date:
2007-06-06
EVLA Correlator Chip ASIC - Response to production CDR Committee report
Start Date:
2007-06-22
EVLA Project Book, Chapter 8: Correlator
Start Date:
2007-08-23
Requirements and Functional Specification: Station Board Filter FPGA
Start Date:
2007-08-25
Requirements and Functional Specification: EVLA Correlator Power Monitor and Control System
Start Date:
2007-10-19
Interface Control Document: External Timecode (ext-TC) and 128 MHz Clock Interface Specification
Start Date:
2007-10-30
Protocol Specification - Station Timecode ("st-TC") Protocol and Physical Interface Specification
Start Date:
2007-10-31
Requirements for the Proposal Management Tool abd the Extension of the Proposal Submission Tool
Start Date:
2008-02-14
Aliasing symptoms
Start Date:
2008-03-00
Overview of the WIDAR Prototype Correlator Testbed - Diagrams, Descriptions, Notes, Questions, Issues
Start Date:
2008-04-23
ESD Chacterization Report for NRC
Start Date:
2008-05-09
Critical On-the-Sky Tests Using the WIDAR Proto-type Correlator
Start Date:
2008-05-26
Protocol Specification - EVLA Correlator Monitor & Control - Virtual Correlator Interface -VCI
Start Date:
2008-06-25
EVLA LO Phase Stability Tests, July 2007-July 2008
Start Date:
2008-07-00
Virtual Correlator Interface - VCI: an overview
Start Date:
2008-07-10
Latch-up Characterization Report for NRC EVLA
Start Date:
2008-07-31
Interface Control Document: EVLA Correlator System Numbering Plan
Start Date:
2008-08-25
Reliability Qualification Report on EVLA ASIC CA2048CL-F672C256-A WIDAR Correlator
Start Date:
2008-08-29
VCI Protocol Review Report
Start Date:
2008-09-09
EVLA CA2048CL-F672C256-A WIDAR Burn-in Report
Start Date:
2008-09-30
Protocol Specifications: HM Gbps Cable Signaling Specification
Start Date:
2008-10-01
WIDAR Schedule Changes and Implications
Start Date:
2008-10-24
10-station Correlator Technical Discussion - 5 November 2008 agenda
Start Date:
2008-11-05
Implementation of Early Science for the EVLA
Start Date:
2008-22-24
EVLA CDR; Station Board and Baseline Board
Start Date:
2008-11-26
Scientific Capabilities Duriing Resident Shared Risk Observing: a strawman proposal for 2010 from an e2e & WIDAR perspective
Start Date:
2009-02-12
EVLA Usecase #1: Continuum Detection Experiment at Ka Band
Start Date:
2009-02-26
EVLA Usecase #2: Redshifted Molecular Absorption in Ka and Q Bands
Start Date:
2009-02-26
Hardware and Software Setup of WIDAR-0
Start Date:
2009-09-08